Registering Property in India, Lucknow
BUILDING A WAREHOUSEData as of: January 2006
City: Lucknow
Registration Requirements:
| Procedure 1 | Obtain land use permission |
| Time to complete: | 60 days |
| Cost to complete: | INR 10000 |
| Comment: | This document is issued by the Lucknow Development Authority or by U.P. Housing and Development Board. There are the two regulatory agencies established in Lucknow district. Both of these have their separate jurisdiction. However, with each of these autho |
| Procedure 2 | Apply for building permit and pay initial fee |
| Time to complete: | 5 days |
| Cost to complete: | INR 3,000 |
| Comment: | The company must submit the application to Lucknow Development Authority or by U.P. Housing and Development Board along with the relevant documents (maps and plans). |
| Procedure 3 | Obtain approval of plans (building permit) and pay final fees |
| Time to complete: | 50 days |
| Cost to complete: | INR 30,000 |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. The Con |
| Procedure 4 | Notify the Lucknow Development Authority about commencement of earth work for foundation |
| Time to complete: | 45 days |
| Cost to complete: | INR 5,000 (fee for all inspections) |
| Comment: | Normally, officials of the Lucknow Development Authority (LDA) inspect the premises during construction. |
| Procedure 5* | Receive foundation inspection and commencement certificate |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 6* | Notify the Lucknow Development Authority before the start of foundation concreting |
| Time to complete: | 43 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 7* | Receive foundation concreting inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 8* | Notify the Lucknow Development Authority before the start of laying the roof and basement floor work |
| Time to complete: | 41 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 9* | Receive roof inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 10* | Notify the Lucknow Development Authority about of completion finishing work |
| Time to complete: | 39 days |
| Cost to complete: | no charge |
| Comment: | The company should inform the local authority about completion of the finishing work (white waxing, coloring, fixing, water supply, drainage, or other sanitary fitments), before obtaining regular connection for water supply/electricity. |
| Procedure 11* | Receive finishing work inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12 | Obtain no objection certificate from fire department |
| Time to complete: | 30 days |
| Cost to complete: | INR 2,500 |
| Comment: | |
| Procedure 13* | Receive inspection from fire department |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 14* | Apply for the use and uplift of underground water with U.P. pollution control board |
| Time to complete: | 15 days |
| Cost to complete: | INR 5,000 |
| Comment: | |
| Procedure 15* | Receive inspection from U.P. pollution control board |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 16* | Obtain no objections certificate from Public Health Department |
| Time to complete: | 15 days |
| Cost to complete: | INR 3,500 |
| Comment: | |
| Procedure 17* | Apply for sanction of power connection with Uttar Pradesh Power Corporation |
| Time to complete: | 45 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | |
| Procedure 18* | Receive inspection from Uttar Pradesh Power Corporation |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 19* | Obtain water and sewage connection from Lucknow Nagar Nigam |
| Time to complete: | 40 days |
| Cost to complete: | INR 11,250 (INR 7,500 –15,000) |
| Comment: | |
| Procedure 20* | Obtain phone connection |
| Time to complete: | 7 days |
| Cost to complete: | INR 2,000 |
| Comment: | |
| Procedure 21 | Obtain occupancy permit |
| Time to complete: | 20 days |
| Cost to complete: | INR 2,500 |
| Comment: | There is no completion certificate in Lucknow. |
| Procedure 22* | Receive final inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: |