Registering Property in India, Hyderabad

BUILDING A WAREHOUSE
Data as of: January 2006
City: Hyderabad

Registration Requirements:
Procedure 1Obtain land use permission from Hyderabad Urban development authority
Time to complete:3 days
Cost to complete:INR 12,050 (INR 10,000-14,100)
Comment:
Procedure 2Apply for building permit and No Objection Certificate and pay initial fee
Time to complete:5 days
Cost to complete:INR 11500
Comment:The company must submit the application in Form A to the Hyderabad Urban Development Authority along with the following documents: a) Building application duly signed by the owner; b) Builder and architect, engineer; c) Declaration forms duly signed by th
Procedure 3Obtain approval of plans (building permit) and pay final fees
Time to complete:30 days
Cost to complete:INR 30000
Comment:Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. Once th
Procedure 4Notify the Municipal Corporation about commencement of earth work for foundation
Time to complete:45 days
Cost to complete:INR 5,000 (fee for all inspections)
Comment:
Procedure 5*Receive foundation inspection and commencement certificate
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 6*Notify the Municipal Corporation before the start of foundation concreting
Time to complete:43 days
Cost to complete:no charge
Comment:
Procedure 7*Receive foundation concreting inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 8*Notify the Municipal Corporation before the start of laying the roof and basement floor work
Time to complete:41 days
Cost to complete:no charge
Comment:
Procedure 9*Receive roof inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 10*Notify the Municipal Corporation about of completion finishing work
Time to complete:39 days
Cost to complete:no charge
Comment:The company should inform the local authority about completion of the finishing work (white waxing, coloring, fixing, water supply, drainage, or other sanitary fitments), before obtaining regular connection for water supply/electricity.
Procedure 11*Receive finishing work inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 12Obtain no objection certificate from fire department
Time to complete:30 days
Cost to complete:INR 2500
Comment:
Procedure 13*Receive inspection from fire department
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 14*Apply for the use and uplift of underground water with the Andhra Pradesh pollution control board
Time to complete:15 days
Cost to complete:INR 5000
Comment:
Procedure 15*Receive inspection from Andhra Pradesh pollution control board
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 16*Obtain no objections certificate from Public Health Department
Time to complete:10 days
Cost to complete:INR 3500
Comment:
Procedure 17*Apply for sanction of power connection with A.P. Central Power Distribution Company
Time to complete:45 days
Cost to complete:INR 75,000 (INR 50,000-100,000)
Comment:
Procedure 18*Receive inspection from A.P. Central Power Distribution Company
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 19*Obtain water and sewage connection from Hyderabad Metropolitan Water Supply and Sewerage Board
Time to complete:15 days
Cost to complete:INR 7500
Comment:
Procedure 20*Obtain phone connection
Time to complete:7 days
Cost to complete:INR 2000
Comment:
Procedure 21Obtain completion certificate
Time to complete:20 days
Cost to complete:INR 2500
Comment:
Procedure 22*Receive final inspection
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment:
Procedure 23Obtain occupancy permit
Time to complete:15 days
Cost to complete:INR 2500
Comment:
Procedure 24*Receive inspection for obtaining occupancy permit
Time to complete:1 day (included in previous procedure)
Cost to complete:no charge
Comment: